Maths 4 weavers can weave 4 mats in 4 days, how many mats can be woven by 8 weavers in 8 days at the same speed?

Q.201348: 4 weavers can weave 4 mats in 4 days, how many mats can be woven by 8 weavers in 8 days at the same speed?
A
B
C
D
Previous Languge/भाषा Next
कृपया शेयर करें=>


More quiz in Hindi

चक्रवृद्धि Quiz Mcqs
लाभ एवं हानि Quiz Mcqs
अनुपात Quiz Mcqs
औसत Quiz Mcqs
आयतन Quiz Mcqs
घड़ी Quiz Mcqs

 Maths in english,  compund proportion  question answers in english pdf   questions in english, Know About Maths online test Maths MCQS Online Coaching in english quiz book    

Comments।




भाषा चयन करें
Select Language
हिन्दी
English