Maths A contractor took a contract to complete a work in 38 days and employed 30 persons, after 25 days he employed 5 more persons and finished the work 1 day before the scheduled time, if he did not employ additional persons, how many days before the appointed time After the work ends?

Q.201352: A contractor took a contract to complete a work in 38 days and employed 30 persons, after 25 days he employed 5 more persons and finished the work 1 day before the scheduled time, if he did not employ additional persons, how many days before the appointed time After the work ends?