Maths A contractor took a contract to complete the construction work of a road in 200 days and he employed 140 men on less, after 60 days he came to know that 1/4th of the total work has been completed, how many additional persons should he employ? Finished work on time?

Q.201371: A contractor took a contract to complete the construction work of a road in 200 days and he employed 140 men on less, after 60 days he came to know that 1/4th of the total work has been completed, how many additional persons should he employ? Finished work on time?