Maths If 8 men working 9 hours a day can complete a wall 18 meters long, 2 meters high in 10 days, then how many men 32 meters long, 3 meters wide and 9 meters high can complete them in 8 days working 6 hours a day?

Q.201377: If 8 men working 9 hours a day can complete a wall 18 meters long, 2 meters high in 10 days, then how many men 32 meters long, 3 meters wide and 9 meters high can complete them in 8 days working 6 hours a day?