Maths A contract was given for 56 days to complete a work, 104 people were engaged on it, working 8 hours a day, 2/5 of the work was completed in 30 days, how many more people should be employed that now work 9 hours a day and complete the work on time go?

Q.201378: A contract was given for 56 days to complete a work, 104 people were engaged on it, working 8 hours a day, 2/5 of the work was completed in 30 days, how many more people should be employed that now work 9 hours a day and complete the work on time go?