Maths A can do 1/2 of a work in 5 days, B can do 3/5 of the work in 9 days and C can do 2/3 of the work in 8 days. finish the day?

Q.201417: A can do 1/2 of a work in 5 days, B can do 3/5 of the work in 9 days and C can do 2/3 of the work in 8 days. finish the day?