Maths A alone can do a piece of work in 12 days and B alone can do it in 18 days. Both of them started the work together but A left the work 3 days before the completion of the work. In how many days the whole work was completed?

Q.201436: A alone can do a piece of work in 12 days and B alone can do it in 18 days. Both of them started the work together but A left the work 3 days before the completion of the work. In how many days the whole work was completed?