10 persons start a work but after some days 4 persons leave the work, as a result of this the work which was to be completed in 40 days was completed in 50 days, after how many days did 4 persons leave the work?

Q.201466: 10 persons start a work but after some days 4 persons leave the work, as a result of this the work which was to be completed in 40 days was completed in 50 days, after how many days did 4 persons leave the work?