Maths A and B together can finish a work in 12 days while B and C can do it in 16 days first A worked on it for 5 days then B worked for 7 days and rest of the work was done by C in 13 days In how many days will C alone complete the work?

Q.201493: A and B together can finish a work in 12 days while B and C can do it in 16 days first A worked on it for 5 days then B worked for 7 days and rest of the work was done by C in 13 days In how many days will C alone complete the work?